18 Jun 2026
5. PC500 KGU (22 - 28 JUNI 2026) WELDING LOWER AND UPPER STRUCTURE
IKK PANAS · PLANT
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
SUTARNO
Lokasi
PIT KGU
Register
BIB/HSE/IKK/2026/VI/11697
Layanan Publik
Pantau status pengajuan IKK, approval, dan closing tanpa menu yang berlebihan.
Total
650
Data masuk
Open
21
Aktif
Close
629
Selesai
Done Closing
192
Tuntas
Fokus Saat Ini
02 Jul 2026 | COE | AREA TOWER BLC189
Filter data
Daftar Monitoring
Data ditampilkan ringkas agar mudah dipindai.
18 Jun 2026
IKK PANAS · PLANT
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
SUTARNO
Lokasi
PIT KGU
Register
BIB/HSE/IKK/2026/VI/11697
18 Jun 2026
IKK PANAS · PLANT
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
SUTARNO
Lokasi
PIT KGU
Register
BIB/HSE/IKK/2026/VI/11696
18 Jun 2026
IKK PANAS · PLANT
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
SUTARNO
Lokasi
PIT KGU
Register
BIB/HSE/IKK/2026/VI/11695
18 Jun 2026
IKK PANAS · PLANT
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
SUTARNO
Lokasi
PIT KGU
Register
BIB/HSE/IKK/2026/VI/11694
18 Jun 2026
IKK PANAS · PLANT
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
SUTARNO
Lokasi
PIT KGU
Register
BIB/HSE/IKK/2026/VI/11652
17 Jun 2026
IKK PANAS · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
HENDRIKUS
Lokasi
OFFICE DEWATERING & HV
Register
BIB/HSE/IKK/2026/VI/11611
17 Jun 2026
IKK PANAS · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
HENDRIKUS
Lokasi
WORKSHOP SUPPORT
Register
BIB/HSE/IKK/2026/VI/11609
17 Jun 2026
IKK PANAS · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
HENDRIKUS
Lokasi
WORKSHOP TAMPORARY
Register
BIB/HSE/IKK/2026/VI/11608
17 Jun 2026
IKK KETINGGIAN · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
LILI SUHERLI
Lokasi
WORKSHOP TAMPORARY
Register
BIB/HSE/IKK/2026/VI/11607
17 Jun 2026
IKK PANAS · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
HENDRIKUS
Lokasi
PPA MART
Register
BIB/HSE/IKK/2026/VI/11606
17 Jun 2026
IKK PANAS · TSP
Tanggal Pekerjaan
22 Jun 2026
Pemegang Izin
HARI ANWAR
Lokasi
PIT KGU ATAU ASSEMBLY
Register
BIB/HSE/IKK/2026/VI/11591
17 Jun 2026
IKK PANAS · TSP
Tanggal Pekerjaan
20 Jun 2026
Pemegang Izin
HARI ANWAR
Lokasi
RAJAWALI
Register
BIB/HSE/IKK/2026/VI/11588
17 Jun 2026
IKK KETINGGIAN · COE
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
SETIARDI INDRA K.
Lokasi
ALL AREA PPA
Register
BIB/HSE/IKK/2026/VI/11587
17 Jun 2026
IKK KETINGGIAN · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
LILI SUHERLI
Lokasi
KLINIK PPA
Register
BIB/HSE/IKK/2026/VI/11579
17 Jun 2026
IKK KETINGGIAN · PJM
Tanggal Pekerjaan
19 Jun 2026
Pemegang Izin
LILI SUHERLI
Lokasi
PROJECT OFFICE DEWATERING DAN HIGH VOLTAGE
Register
BIB/HSE/IKK/2026/VI/11577
| Tgl Pengajuan | Jenis Izin | Judul Izin | Tgl Pekerjaan | Dept/Perusahaan | Pemegang Izin | Lokasi | No Register | Status | Status Approval | Status Closing |
|---|---|---|---|---|---|---|---|---|---|---|
| 18 Jun 2026 | IKK PANAS | 5. PC500 KGU (22 - 28 JUNI 2026) WELDING LOWER AND UPPER STRUCTURE | 22 Jun 2026 | PLANT | SUTARNO | PIT KGU | BIB/HSE/IKK/2026/VI/11697 | CLOSE | FULL APPROVAL | - |
| 18 Jun 2026 | IKK PANAS | 4. PC850 KGU (22 - 28 JUNI 2026) WELDING LOWER AND UPPER STRUCTURE | 22 Jun 2026 | PLANT | SUTARNO | PIT KGU | BIB/HSE/IKK/2026/VI/11696 | CLOSE | FULL APPROVAL | - |
| 18 Jun 2026 | IKK PANAS | 3. PC1250 KGU (22 - 28 JUNI 2026) WELDING LOWER AND UPPER STRUCTURE | 22 Jun 2026 | PLANT | SUTARNO | PIT KGU | BIB/HSE/IKK/2026/VI/11695 | CLOSE | FULL APPROVAL | - |
| 18 Jun 2026 | IKK PANAS | 2. PC2000 KGU (22 - 28 JUNI 2026) WELDING LOWER AND UPPER STRUCTURE | 22 Jun 2026 | PLANT | SUTARNO | PIT KGU | BIB/HSE/IKK/2026/VI/11694 | CLOSE | FULL APPROVAL | - |
| 18 Jun 2026 | IKK PANAS | 1. PC3400 KGU (22 - 28 JUNI 2026) WELDING LOWER AND UPPER STRUCTURE | 22 Jun 2026 | PLANT | SUTARNO | PIT KGU | BIB/HSE/IKK/2026/VI/11652 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK PANAS | PJM - FABRIKASI BAJA - OFFICE DEWATERING & HV - 19-25 JUNI 2026 | 19 Jun 2026 | PJM | HENDRIKUS | OFFICE DEWATERING & HV | BIB/HSE/IKK/2026/VI/11611 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK PANAS | PJM - FABRIKASI BAJA - WORKSHOP SUPPORT - 19-25 JUN 2026 | 19 Jun 2026 | PJM | HENDRIKUS | WORKSHOP SUPPORT | BIB/HSE/IKK/2026/VI/11609 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK PANAS | PJM - IZIN PANAS PEMBONGKARABN DOME - WORKSHOP TAMPORARY - 19-25 JUNI 2026 | 19 Jun 2026 | PJM | HENDRIKUS | WORKSHOP TAMPORARY | BIB/HSE/IKK/2026/VI/11608 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK KETINGGIAN | PJM - IZIN KETINGGIAN PEMBONGKARN DOME - WORKSHOP TAMPORARY - 19-25 JUNI 2026 | 19 Jun 2026 | PJM | LILI SUHERLI | WORKSHOP TAMPORARY | BIB/HSE/IKK/2026/VI/11607 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK PANAS | PJM - PENGELASAN BESI PLAT - PPA MART - 19-25 JUNI 2026 | 19 Jun 2026 | PJM | HENDRIKUS | PPA MART | BIB/HSE/IKK/2026/VI/11606 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK PANAS | TSP - REPAIR CRACK & LINE BORING ATTACHMENT PC2000 - PIT KGU ATAU ASSEMBLY - 22-28 JUNI 2026 | 22 Jun 2026 | TSP | HARI ANWAR | PIT KGU ATAU ASSEMBLY | BIB/HSE/IKK/2026/VI/11591 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK PANAS | TSP - MAKE SAFETY BLASTING MULTIFLOW - RAJAWALI - 20-26 JUNI 2026 | 20 Jun 2026 | TSP | HARI ANWAR | RAJAWALI | BIB/HSE/IKK/2026/VI/11588 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK KETINGGIAN | COE - INSTALASI PERANGKAT WIRELES - ALL AREA PPA - 19-25 JUNI 2026 | 19 Jun 2026 | COE | SETIARDI INDRA K. | ALL AREA PPA | BIB/HSE/IKK/2026/VI/11587 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK KETINGGIAN | PJM - RENOVASI KLINIK - KLINIK PPA - 19-25 JUNI 2026 | 19 Jun 2026 | PJM | LILI SUHERLI | KLINIK PPA | BIB/HSE/IKK/2026/VI/11579 | CLOSE | FULL APPROVAL | - |
| 17 Jun 2026 | IKK KETINGGIAN | PJM - PEMBANGUNAN OFFICE DEWATERING DAN HIGH VOLTAGE - PROJECT OFFICE DEWATERING DAN HIGH VOLTAGE - 19-25 JUNI 2026 | 19 Jun 2026 | PJM | LILI SUHERLI | PROJECT OFFICE DEWATERING DAN HIGH VOLTAGE | BIB/HSE/IKK/2026/VI/11577 | CLOSE | FULL APPROVAL | - |